Closed Work Order is displayed in MRP Detail Inquiry

MRP Detail Inquiry shows data for closed Work Order WO status = "C".
We run option 23.25.1 Rebuild "mrp_det" table and then run 23.2 Regenerate Materials Plan but still the problem was not solved. The WO is still getting displayed. Can u please guide us through this problem ?
 

comatt1

Member
MRP Detail Inquiry shows data for closed Work Order WO status = "C".
We run option 23.25.1 Rebuild "mrp_det" table and then run 23.2 Regenerate Materials Plan but still the problem was not solved. The WO is still getting displayed. Can u please guide us through this problem ?

A little backround is needed. If this is a single work order that consistently gets regenerated, is this the only one?

Kishor is correct, it shouldn't be possible, and I would have run the regen.

I am sure that something can be evaluated if more information is provided.

What I think I know from your post:

- There is a WO released that runs to completion
- MRP regen recreates that same WO# or a different # with the same SO referenced?

Is there something special about the order: sub-products, kits?

Been so long since I have worked directly with MRP. My first course of action would be to talk with Mfg/Pro support.
 